Lavon Data Center: What’s Proposed, Where It Stands & What It Could Mean

Is a data center coming to Lavon? In short, here’s what public records show about the Elevon site on FM 2755, the city’s proposed data center moratorium and the larger wave of North Texas data center projects.

To be clear, our goal isn’t to promote or oppose any project. Instead, we collect public information, explain it in plain language and help Lavon residents ask informed questions.

Modern data center campus and electrical infrastructure in North Texas
As of October 19, 2026

Lavon Data Center at a Glance

Zoned Site
79.3 ac
Elevon Parcels 8 & 9, southwest of FM 2755 and Watkins Road
Data Center Use Added
Dec 2024
Council amended the Elevon zoning on December 3, 2024
Moratorium Hearing
Oct 20
Second of two public hearings, 6:30 p.m., Lavon City Hall
End User
None
No data center operator publicly announced in city records we reviewed

Sources: City of Lavon Planning & Zoning agenda (Nov. 26, 2024) and City Council agendas (Dec. 3, 2024; Aug. 6, 2026; Oct. 20, 2026).

Lavon, TX 75166 · Collin County

Is a Data Center Being Built in Lavon, TX?

Not yet. Currently, Lavon has land zoned to allow a data center, but no operator has been publicly announced and no construction has begun. Meanwhile, the City Council is considering a temporary moratorium on new data center permits.

Proposed Lavon data center site: key facts from public records
Item What the Record Shows
LocationAbout 79.3 acres southwest of FM 2755 (McClendon Road) and Watkins Road (CR 541), within the Elevon planned development
Zoning parcelsElevon Land Use Parcels 8 and 9 (Business Park)
Applicant / ownerApplicant Lovett Industrial; property owner Petro-Hunt L.L.C.
What was requestedDefine “data center” as a permitted use and revise screening, dimensional standards, building materials and setbacks
ApprovalsPlanning & Zoning recommended approval after its November 26, 2024 hearing; City Council adopted the amendment (Ordinance No. 2024-12-01) on December 3, 2024
Utilities nearbyGarland Power & Light serves the area, with a planned substation just south, according to the Lavon EDC’s Business-Technology Park listing
OperatorNone publicly announced as of October 19, 2026
About “Project Lavon” listings

Notably, a third-party data center directory lists a 40 MW “Project Lavon” on FM 2755. However, we haven’t found city records confirming that project, its operator or its size. Therefore, treat directory listings as unverified until they appear in city agendas or official filings.

Timeline

Lavon Data Center Timeline

Over time, here’s how the Lavon data center question has developed, alongside the statewide actions that affect it.

Lavon data center timeline
Date Event
Nov. 26, 2024Lavon Planning & Zoning Commission holds a hearing on Lovett Industrial’s request to allow a data center on Elevon Parcels 8 and 9.
Dec. 3, 2024With P&Z and staff recommending approval, the City Council holds a public hearing and adopts the amendment (Ordinance No. 2024-12-01), adding data centers as a permitted use on the site.
Summer 2026Residents form groups, start online petitions and speak at city and county meetings, asking for transparency about a possible hyperscale data center.
July 21–22, 2026Residents comment on data center use at the July 21 council meeting. The next day, a planned evening information session is cancelled, and developers’ representatives instead meet with residents at City Hall.
Aug. 3, 2026Statewide, Gov. Abbott directs ERCOT and the PUC to audit data center grid-connection requests, effectively pausing new interconnections during the review.
Aug. 6, 2026At a special meeting, the Lavon City Council takes up “land use and a temporary moratorium relating to potential data center development.”
Sept. 21, 2026Next, the governor orders TCEQ to stop issuing new environmental permits for data centers until state audits are complete.
Oct. 20, 2026Lavon City Council holds the second of two public hearings on a temporary data center moratorium, followed by discussion and the first reading of the ordinance.
How to follow the Lavon data center moratorium

First, the City of Lavon posts agendas and meeting packets on its website before each council meeting. In addition, residents can speak during public hearings. After the council acts, we’ll update this page.

Near Lavon

Data Center Activity Near Lavon

Lavon isn’t the only nearby community weighing data centers. In fact, several neighbors have recent proposals or new zoning rules.

Royse City Area

GIGA took over a proposed data center on CR 2656 in unincorporated Hunt County, east of Royse City, and held a town hall in July 2026. Earlier, a similar application in Quinlan was withdrawn.

Wylie

Closer to home, Wylie approved a 59.8-acre rezoning in April 2026 that included limits on data center use.

Princeton

Similarly, Princeton staff began evaluating zoning amendments to regulate data centers in June 2026.

Start With the Basics

What Is a Data Center?

A data center houses computer servers, networking equipment and storage systems, plus the infrastructure that keeps them running. Essentially, it powers cloud services, artificial intelligence, online apps, financial systems and streaming.

Computing Equipment

At the core, servers process and store the information used by websites, apps, cloud computing and AI systems.

Electrical Infrastructure

Data centers need reliable power, along with transformers, substations and backup generators for continuous operation.

Cooling Systems

Because servers generate heat, facilities rely on cooling that may use air, water or other technologies.

North Texas Development

Why Are Data Centers Coming to Lavon and North Texas?

Developers weigh many factors when choosing a site. For example, North Texas offers a major metro area along with extensive electrical, telecommunications and transportation infrastructure.

As a result, fast-growing communities on the edge of Dallas-Fort Worth, including Lavon, increasingly see interest in large tracts of business-park land.

Common Site-Selection Factors
  • Large tracts of developable land
  • Access to electrical transmission
  • Fiber and telecommunications connectivity
  • Proximity to Dallas-Fort Worth
  • Utility and water capacity
  • Local zoning and economic-development conditions
Looking at Both Sides

Data Center Benefits and Community Concerns

Individual projects differ substantially. So, rather than assuming every data center has the same impact, it’s useful to examine the specifics of each proposal.

Potential Community Benefits

  • Private investment in land, buildings and equipment
  • Construction work for contractors, electricians and engineers
  • Permanent jobs in technical, security and maintenance roles
  • Local tax base, depending on valuation and agreements
  • Infrastructure upgrades to power, fiber or roads

Common Community Concerns

  • Electricity demand from large facilities
  • Water use, depending on the cooling technology
  • Noise from cooling equipment, transformers and generators
  • New infrastructure, such as substations and transmission lines
  • Proximity to homes, including setbacks, lighting and screening
Power, Water & Noise

How Much Power and Water Do Data Centers Use?

Electricity

Demand varies widely by size and purpose. However, large data centers use far more power than typical commercial buildings because servers and cooling run around the clock. Useful questions include expected demand, new transmission needs and any on-site generation.

Water & Cooling

There’s no single number. Instead, water use depends on cooling technology: evaporative systems use more, while closed-loop and air-cooled designs use less. Ask how much water, from where, and whether municipal drinking water will be used.

Noise

Fans, chillers, transformers and backup generators can create sound. Also, generators may be tested even without an outage. Consequently, the effect on neighbors depends on design, sound barriers, setbacks and distance.

Worth knowing

At the state level, ERCOT has requested information from large data center developers about grid dependency, on-site generation, water, cooling, noise, lighting, traffic and public financial assistance. Source: ERCOT Data Center Impact Request for Information.

Evaluate the Project

Questions to Ask About a Proposed Lavon Data Center

Specific questions are more useful than simply deciding whether data centers are good or bad. Whether you support or oppose a project, these are worth asking at a public hearing.

Electricity

  • How much power will the finished facility need?
  • Will new substations or transmission lines be built?
  • Will it generate its own power?
  • What backup power is planned?

Water

  • How much water will it consume?
  • Where will the water come from?
  • What cooling technology will be used?
  • Will drinking water be used for cooling?

Noise & Neighbors

  • How close will it be to existing homes?
  • What sound levels are expected at the property line?
  • How often will generators be tested?
  • What sound-reduction measures are planned?

Economic Impact

  • What private investment is projected?
  • How many construction and permanent jobs?
  • What tax revenue is expected?
  • Are incentives or abatements requested?

Infrastructure

  • Will roads need improvements?
  • Will water or wastewater lines need expansion?
  • Who pays for new infrastructure?

Where to Look

  • City council and P&Z agendas
  • County and appraisal district records
  • ERCOT and PUC filings
  • Announced development agreements
Known Facilities & Announced Plans

North Texas Data Center Tracker

Below is a summary of publicly reported data centers that are operating, under construction or proposed in North Texas and across the state. Of course, inclusion isn’t an endorsement of, or objection to, any project. Moreover, capacity, investment and timeline figures are as reported by the cited sources and may change.

~150–410
Operating data centers in Texas, depending on how facilities are counted
380+
Planned or proposed data center projects statewide
~421 GW
Data center power requests in ERCOT’s large-load queue (June 2026)
~85.5 GW
ERCOT’s all-time peak electricity demand, for comparison

Counts vary widely between trackers. Cleanview lists 147 operating and 386 planned projects; Google cited 411 Texas data centers in November 2025. A request in the ERCOT queue doesn’t mean a project will be built, which is one reason the state ordered an audit in August 2026.

North Texas: Operating, Under Construction & Proposed

The Dallas-Fort Worth region is one of the largest data center markets in the country, and Ellis County has been reported as leading all Texas counties in requested power.

Operating Under construction Proposed / approved Paused / under review
North Texas data center projects
Project / Operator Location Reported Size Status
Elevon site (no operator announced)
Applicant: Lovett Industrial
Lavon, Collin County (FM 2755 & Watkins Rd.)~79.3 acres zonedUnder review
Moratorium hearing Oct. 20, 2026
GIGA
Previously filed as BT Gateway Data Center LLC
CR 2656, unincorporated Hunt County (east of Royse City)~20 developed acres of a 30-acre site; about $384M
Uses existing distribution lines; no tax abatement requested, according to the developer
Proposed
Town hall July 2026; target mid-2027
BlockchAIn Digital Infrastructure
AI / GPU hosting site
Collin CountyNot disclosedUnder construction
Target Q3 2027
FlexentialNear Talty, Kaufman County110 acres; 36 MW first phase, up to ~108 MW
Closed-loop cooling planned
Proposed
Site work early 2027; first customers late 2028
Aligned Data CentersPlano, Collin CountyNot listedOperating
Garland cluster: NTT, Stream (DFW VII), Prime, Digital RealtyGarland, Dallas CountyMultiple campusesOperating
Digital Realty expansion under construction
Established core: Equinix, QTS, Digital Realty, CyrusOneDallas, Irving, Richardson, CarrolltonMultiple campusesOperating
GoogleMidlothian and Red Oak, Ellis CountyTwo campusesOperating
Red Oak opened Nov 2025
Compass DatacentersRed Oak, Ellis County830-acre campus approved May 2026
Approval drew a 2,200+ signature petition; Compass pledged $15M for an animal shelter
Expanding
DataBankRed Oak, Ellis County~480 MWUnder construction
Lincoln PropertyMidlothian area, Ellis County~540 MWProposed
PowerHouse / ProvidentGrand Prairie areaUp to ~1,800 MW campusProposed
STACK Infrastructure; Skybox PowerCampusLancaster area, Dallas CountySkybox: ~300 MWSTACK under construction
Skybox proposed
Hyperscale facilityWilmer, Dallas CountyHyperscaleUnder construction
MetaFort Worth (Alliance)CampusOperating
Black MountainSoutheast Fort Worth450 acres rezoned; about $10BProposed
Edged Data CentersSouthwest Fort Worth (Veale Ranch area)186 acres; about $1BStalled
Tax-break request paused, April 2026
Core ScientificDentonNot listedUnder construction
Riot PlatformsCorsicana, Navarro County~1,000 MWApproved
Other proposalsPrime (Aledo), South Creek Ranch (Ferris)Not listedProposed

Not a complete list. In particular, smaller enterprise and colocation facilities across Dallas, Collin, Denton and Tarrant counties aren’t individually listed.

Major Data Center Projects Elsewhere in Texas

By comparison, many of the largest projects are being built outside major metros, often paired with on-site or dedicated power generation.

Major Texas data center projects outside North Texas
Project / Operator Location Reported Size Status
Stargate (OpenAI, Oracle, Crusoe)Abilene, Taylor County~1.2 GWPartly operating
4 of 8 buildings online as of April 2026
Frontier (Vantage Data Centers; Oracle/OpenAI)Shackelford County~1.4–2 GW; about $25BUnder construction
First building late 2026
Stargate (SB Energy / SoftBank, OpenAI)Milam County~1.2 GWUnder construction
Full build-out targeted 2028
Riot Platforms, RockdaleMilam County~700 MWOperating
Google, three new campusesArmstrong County (1); Haskell County (2)$40B through 2027Announced
November 2025
MetaEl Paso~1 GW; investment raised to $10BUnder construction
Project Matador (Fermi America)Carson County, near AmarilloUp to 11 GW planned (gas, nuclear, solar)Planned
First tenant funding deal ended Dec 2025
TractCaldwell County~2 GW plannedPlanned
First 360 MW targeted 2028
Data City, Texas (Energy Abundance Development Corp.)Near LaredoUp to 5 GW plannedPlanned
Stream Data Centers, San Antonio III–VIIBexar County~200–280 MWOperating
Hut 8, King MountainUpton County~280 MWOperating
Central Texas proposalsNexus (Hill County); Infrakey (near Waco)Infrakey ~925 MW; Nexus multi-GW expansionProposed
Recent Developments

Recent Developments That May Affect These Plans

October 2026 · Lavon

Lavon weighs a moratorium

The City Council scheduled the second of two public hearings on a temporary moratorium on data center permits for October 20, 2026, along with the first reading of the ordinance.

September 2026 · Statewide

State pauses environmental permits

Gov. Abbott ordered TCEQ to stop issuing new environmental permits for data centers until ERCOT and Texas Water Development Board audits are complete.

August 2026 · Statewide

State audit of grid requests

Earlier, the governor directed the PUC and ERCOT to audit data center interconnection requests, including ownership, financing, water use and community impact. As a result, new data center interconnections are effectively paused while roughly 300 projects of 75 MW or more are reviewed, with completion targeted for December 10, 2026.

August 2026 · Fort Worth & Denton

Moratorium processes started

Fort Worth voted unanimously to begin the process for a 90-day pause on new data center construction and created a Data Center and Infrastructure Commission. Likewise, Denton began the legal process for a moratorium.

Sources: City of Lavon Oct. 20, 2026 agenda • Lavon P&Z Nov. 26, 2024 agenda • Lavon Aug. 6, 2026 packet • Lavon EDC • Texas Tribune • Cleanview • North Texas Market Insider • KERA News • POWER Magazine • Utility Dive • NBC DFW • Royse City Herald-Banner • DCD • Green Source DFW • Wylie News • Epoch AI • KSAT • ABC 7 Amarillo

Last updated October 19, 2026. Know of a project we missed or a detail that has changed? Call us at (972) 853-8884, and we’ll review it against public records.

Lavon Data Center FAQ

Frequently Asked Questions

Is a data center being built in Lavon, TX?

Not as of October 19, 2026. Lavon has about 79.3 acres zoned to allow a data center within the Elevon development, but no operator has been publicly announced and no construction has begun.

Where is the proposed Lavon data center site?

The zoned site covers Elevon Land Use Parcels 8 and 9, southwest of FM 2755 (McClendon Road) and Watkins Road (CR 541) in Lavon, Collin County.

Has Lavon approved a data center moratorium?

Not yet. The City Council scheduled the second of two public hearings on a temporary data center moratorium for October 20, 2026, followed by discussion and the first reading of the ordinance.

When did Lavon allow data centers on the Elevon site?

Lovett Industrial requested a zoning amendment to make data centers a permitted use on Elevon Parcels 8 and 9. The Planning & Zoning Commission recommended approval on November 26, 2024, and the City Council adopted the amendment on December 3, 2024.

Do data centers use a lot of electricity?

Large data centers can have substantial electrical requirements. However, demand varies by size, equipment and design, so each project should be evaluated on its projected load.

Do data centers use a lot of water?

It depends on the cooling system. Some facilities use water-intensive evaporative cooling, while others use closed-loop or air-cooled designs that use substantially less water.

Are data centers noisy?

Cooling equipment, transformers and backup generators can create sound. Therefore, the effect on nearby homes depends on facility design, equipment placement, sound mitigation, setbacks and distance.

Can a data center affect nearby property values?

There’s no single answer for every location. Instead, effects may depend on distance, surrounding land uses, screening, noise, infrastructure and broader development patterns.

How can I find out whether a data center is proposed near me?

Start by checking city council and planning-and-zoning agendas, county records, development applications, state filings, ERCOT records and publicly announced development agreements.

Are data centers good or bad for a community?

That depends on the individual project and the community’s priorities. Investment, jobs and tax revenue can be weighed alongside electricity demand, water use, infrastructure needs, noise and proximity to homes.

Our Approach

Information Without Taking Sides

Lavon Insurance is a local, independent agency based in Lavon. Above all, we believe community information should help people understand an issue rather than tell them what position to take.

Because project figures change during planning and construction, investment, power demand, water use, jobs and schedules should be verified against the latest source documents.

Useful Primary Sources

  • City of Lavon council and P&Z agendas
  • ERCOT and the Public Utility Commission of Texas
  • Texas Water Development Board
  • Texas Comptroller and Collin County records
  • Development filings and utility records
More Local Resources

Follow Growth in Lavon and North Texas

In addition, our community trackers follow new construction, development and local news around Lavon.